NLUO PMC CONTRACTOR
SIGNATURE AND SEAL SIGNATURE AND SEAL SIGNATURE AND SEAL
satisfaction of the PMC/ Consultant that he is able to carry out and fulfill the contract, and to give security
therefore if so required by the PMC/ Consultant.
Or, if the contractor (whether an individual firm or incorporated company) shall suffer execution to be
issued or shall suffer any payment under this contract to be attached by or on behalf of any of the creditors
of the contractor.
Or, shall assign or sublet this contract without the consent in writing of the NLUO through the Architect/
consultant or shall charge or encumber this contract or any payment due to which may become due to the
contractor there under :
(a) has abandoned the contract; Or
(b) has failed to commence the work, or has without any lawful excuse under these conditions suspended the
progress of the works for 14 (fourteen) days after receiving from the NLUO through the Architect/
Consultant written notice to proceed, or
I has failed to proceed with the works with such diligence and failed to make such due progress as would
enable the works to be completed within the time agreed upon. Or has failed to remove materials from the
site or to pull down and replace work within seven days after written notice from the NLUO through
Architect/ PMC that the said materials were condemned and reject by the PMC under these conditions. Or
has neglected or failed persistently to observe and perform all or any of the acts, matters or things by this
contract to be observed and performed by the contractor for seven days after written notice shall have been
given to the contactor to observe or perform the same or has to the detriment of good workmanship or in
defiance of the NLUO‘s or Architect’s
Consultant’s instruction to the contrary subject any part of the contract. Then and in any of said cases the
NLUO and or the Architect/ consultant , may not withstanding any previous waiver, after giving seven days
notice in writing to the contractor determine the contract, but without thereby affecting the powers of the
NLUO or the Architect/ consultant or the obligation and liabilities of the contractor the whole of which shall
continue in force as fully as if the contract had not been so determined and as if the works subsequently had
been executed by or on behalf of the contractor. And further the NLUO through the Architect/ Consultant