NLUO PMC CONTRACTOR
SIGNATURE AND SEAL SIGNATURE AND SEAL SIGNATURE AND SEAL
their agents or employees may enter upon and take possession of the work and all plants, tools, scaffoldings,
materials, sheds, machineries lying upon the premises or on the adjoining lands or roads use the same by
means of their own employees or workmen in carrying on and completing the work or by engaging any other
contractor or persons to complete the work and the contractor shall not in any was interrupt or do any act,
matter or thing to prevent or hinder such other contractor or other persons employed for completing and
finishing or using the materials and plants for the work.
When the works shall be completed or as soon thereafter as convenient the NLUO or the Architect/
consultant shall give a notice in writing to the contractor to remove his surplus materials and plants and
should the contractor fail to do so within 14 days after receipt thereof by him the NLUO sell the same by
public auction after due publication, and shall adjust the amount realized by such auction. The contractor
shall have no right to question any of the act of the NLUO incidental to the sale of the materials etc.
22.0 PAYMENT TERMS & CONDITIONS :
85% of the total R.A. Bill submitted shall be paid within 7 (Seven) working days from the date of submission of R.A. Bills to
NLUO subject to condition that PMC/PD(I/c) will certify to Pay the amount. The balance payment deducting the necessary
statutory dues shall be paid only after complete verification of Bill by National Law University Odisha / Project Management
Consultant within 15 days.
24.0 Excise duty, taxes, levies etc.
The contractor shall pay and be responsible for payment of all taxes, duties, levies, royalties, fees, cess or
charges in respect of the works including but not limited to sales tax, tax on works contract excise duty, and
octroi, payable in respect of materials, equipment plant and other things required for the contact. All of the
aforesaid taxes, duties, levies, fees and charges shall be to the contractor’s account and the NLUO shall not
be required to pay any additional or extra amount on this account. Variation of taxes, duties, fees levies etc
if any, till completion of work shall be deemed to be included in the quoted rates and no extra amount on
this account. Variation of taxes, duties, levies etc, if any, till completion of work shall be deemed to be
included in the quoted rates and no extra claim on this account will in any case be entertained. If a new tax