Specifications

53
NLUO PMC CONTRACTOR
SIGNATURE AND SEAL SIGNATURE AND SEAL SIGNATURE AND SEAL
You are also requested to start the work at once in consultation with PMC/NLUO. Please note that the time allowed for completion of
work is 75 days, which shall be reckoned from 3rd day of receipt of this letter or date of handing over the site whichever is later.
Please note that time will be the essence of the contract.
You are further requested to take out necessary insurance covers, indemnity bonds, labour permissions at your cost in terms and
conditions of the contract.
Please acknowledge receipt of this letter.
Architects
COPY to Vice Chancellor of NLUO , for information.
Place :………………….
Date :…………………..