Samsung 5G Station Outdoor Installation Manual Describes product installation and requirement procedure. SM-H303V Document Version 1.
© 2020 SAMSUNG Electronics Co., Ltd. All Rights Reserved. The contents of this document/presentation contain proprietary information that must be kept confidential. No part of this document shall be photocopied, reproduced, stored in a retrieval system, or transmitted, in any form or by any means whether, electronic, mechanical. No warranty of accuracy is given concerning the contents of the information contained in this publication.
Confidential Contents Preface vii Conventions in this Document ....................................................................................................... vii New and Changed Information ......................................................................................................viii Revision History ..............................................................................................................................viii Organization of This Document ..........................
Confidential Contents Chapter 4 Inspect the Installation 54 Appendix A Acronyms 57 Appendix B Standard Torque 58 Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential List of Figures Figure 1. Figure 2. Figure 3. Figure 4. Figure 5. Figure 6. Figure 7. Figure 8. Figure 9. Figure 10. Figure 11. Figure 12. Figure 13. Figure 14. Figure 15. Figure 16. Figure 17. Figure 18. Figure 19. Figure 20. Figure 21. Figure 22. Figure 23. Figure 24. Figure 25. Figure 26. Figure 27. Figure 28. Figure 29. Figure 30. Figure 31. Figure 32. Figure 33. Figure 34. Figure 35. Figure 36. Figure 37. Figure 38. Figure 39. Figure 40. Figure 41. Figure 42. Figure 43. Figure 44.
Confidential List of Tables Table 1. Table 2. Table 3. Table 4. Table 5. Table 6. Table 7. Table 8. Table 9. Table 10. Table 11. Table 12. Table 13. Table 14. Table 15. Table 16. Table 17. Table 18. Table 19. Table 20. Table 21. Table 22. Table 23. Table 24. Table 25. Basic Installation Tools ..................................................................................................................... 6 Parts and Tools for Replacing the SIM ..........................................................
Confidential Preface This manual describes how to install a 5G Customer Premises Equipment (CPE) Outdoor and how to connect its cables. This manual includes the following 5G CPE Outdoor: • CPE Outdoor Conventions in this Document Samsung Networks product documentation uses the following conventions. Symbols Symbol Description Indicates a task. Indicates a shortcut or an alternative method. Provides additional information.
Confidential Preface User Input and Console Screen Output Text Input and output text is presented in the Courier font. For example, context CLI commands are presented in bold small caps. For example, Type the RTRV-NE-STS command in the input field. New and Changed Information This section describes information that has been added/changed since the previous publication of this manual. Change Type Change Description Changed Changed ‘Interface Cable Connection’ in Chapter 3.
Confidential Preface Personal and Product Safety This product safety information includes American directives, which you must follow. If these do not apply in your country, please follow similar directives that do apply in your country. Proposition 65 Warning (US Only) State of California Proposition 65 Warning (US only) WARNING: This product contains chemicals known to the State of California to cause cancer and birth defects or other reproductive harm.
Confidential Preface Environment The product must be operated in an environment with the specified relative humidity and ambient temperature ranges. Keep all liquids away from the equipment as accidental spillage can cause severe damage. Anti-Static Precautions The circuit boards and other modules in the product are sensitive to and easily damaged by static electricity.
Confidential Preface Equipment Markings This marking on the product, accessories or literature indicates that the product and its electronic accessories (e.g. charger, headset, USB cable) should not be disposed of with other household waste at the end of their working life. To prevent possible harm to the environment or human health from uncontrolled waste disposal, please separate these items from other types of waste and recycle them responsibly to promote the sustainable reuse of material resources.
Confidential Chapter 1 Before Installation This chapter introduces CPE Outdoor and describes the items that you should know before installation. System View and External Interface This section provides the pictorial view of the CPE Outdoor and its interfaces. CPE Outdoor View Figure below depicts the physical structure of the CPE Outdoor. Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 1 Before Installation Figure 1. CPE Outdoor View 3.54 (90) 3.32 (84.4) Unit: in. (mm) [Top View] 12.75 (323.8) 7.87 (199.8) [Left View] [Front View] [Right View] [Rear View] [Bottom View] An Ethernet cable is not supplied in the package. Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 1 Before Installation CPE Outdoor External Interface Figure below depicts the external interface structure of the CPE Outdoor. Figure 2. CPE Outdoor External Interface [Bottom View] SIM Card Slot (Under USB Cover) Factory Reset Button (Under USB Cover) USB Port (Under USB Cover) LAN Port Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 1 Before Installation Cautions for Installation Observe the safety instructions described in this section when installing the system. Installation must be done in accordance with the applicable local electric codes. Before Installing • Post warning signs in areas where high-voltage cables are installed. • Post ‘off limit’ signs in areas where accidents are most expected. • Use guardrails or fences to block open areas such as ditches, open roof areas, and scaffolds.
Confidential Chapter 1 Before Installation After Installing Remove any debris produced during the work and clean up the installation site. Ensure that the workers do not damage installed cables while cleaning the system. While cleaning the power supply device, take precaution that the device does not come in contact with foreign objects that may cause power failure. Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 1 Before Installation Installation Tools Table below lists the basic tools needed for installation. The additional tools required for each site need to be identified and arranged during a site survey before starting the installation. Table 1. Basic Installation Tools Number Name Specification Purpose of use 1 Torque Driver Apply a torque range : 2–10 lbf·in For fastening M3 Screw (T10) Apply a torque range : 6–22 lbf·in For fastening M4 (Hex.
Confidential Chapter 1 Before Installation 11 Level Normal For horizontality and verticality 12 Hammer Drill Normal Wall type drilling 13 Concrete Drill Bit 1/4 in. (6 mm) For making a hole for inserting Plastic anchor 14 Cable Cutter 0.24–1.26 in. (6–32 mm) Cable cutting 15 Crimping Tool 14 AWG–4 AWG (1.5–16 mm2) Pressure terminal for crimping 16 Cable Stripper Apply cable thickness: 1.5–6.2 in.
Confidential Chapter 1 Before Installation 23 Heating Gun 50–300 °C Shrinking Heat Shrink Tube The required installation tools may vary depending on the conditions at the site. In addition to the basic tools, a protractor, compass, GPS receiver, ladder, safety equipment, cleaning tools, and so on should also be prepared in consideration of the site conditions. Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System This chapter describes installation procedure of the CPE Outdoor. Installation Procedure Figure below depicts the procedure to install the CPE Outdoor. Figure 3. Procedure to Install the CPE Outdoor Foundation Work Bringing in Items Unpacking and Transporting Unpacking Items Pole Type Fixing System Wall Type Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System System Arrangement A minimum distance must be secured around the CPE Outdoor, in each direction for installation and maintenance. Figure below depicts the minimum distance that must be secured for pole type installation of the CPE Outdoor. Figure 4. CPE Outdoor Arrangement Pole type Installation Unit: in. (mm) 8.09 (205.5) W: 7.87 (199.8) H: 12.75 (323.
Confidential Chapter 2 Installing System Transporting and Unpacking This section details how to transport the items to the installation place and describes the procedure to unpack cabinets and other components. Bringing in Items Take care of the following at each stage of transportation of the items: • Check storage place for the system and remove obstacles in advance. • Fasten the system firmly to the transport vehicle or carrier to prevent damage to the system from a vibration or shock.
Confidential Chapter 2 Installing System Item List Figure below depicts the packed item list. Figure 6. Item List CPE Outdoor with attached Unit Bracket Mounting Bracket Assembly Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System Fixing System This section details the procedure to fix the CPE Outdoor. Replacing SIM Before shipping the CPE Outdoor, a SIM should be inserted to it. If replacing a SIM, refer to the following prodedures below. To replace the Subscriber Identity Module (SIM) 1 Ensure that the items mentioned in below table are available. Table 2.
Confidential Chapter 2 Installing System Figure 8. Replacing SIM (2) SIM Card Slot Removing a SIM 6 Place a new SIM card to the SIM card tray with the gold-colored contacts facing downwards. 7 Insert the tray back into the tray slot. Figure 9. Replacing SIM (2) SIM Card Slot New SIM 8 Fix the USB cover by fastening screws in numerical order (1 2 3 4). When fastening the number two screw, be sure to put a chain assembly under the screw first. Samsung 5G Station Outdoor Installation Manual v1.
Confidential Chapter 2 Installing System Figure 10. Replacing SIM (3) M3 Screw USB Cover When fixing the USB cover, make sure to check the order of screw fastening and standard torque value (4.4 lbfin). Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System Fixing System on a Pole Type The CPE Outdoor can be fixed on pole. This section details both procedures. To fix a Mounting Bracket Assembly on the pole 1 Ensure that the items mentioned in below table are available. Table 3.
Confidential Chapter 2 Installing System Figure 12. Fixing Mounting Bracket Assembly on the Pole (3) If it is level, the bubble of the spirit level is positioned at the center of both lines. When fixing the mounting bracket assembly on the pole, be sure to check the level of bracket. After finishing the installation, adjust the level minutely. When poor leveling happens, adjust the position of fasteners used to fix the mounting bracket assembly.
Confidential Chapter 2 Installing System Figure 13. Fixing CPE Outdoor on the Pole Mounting Bracket Assembly Hook groove of the Mounting Bracket Assembly M5 SEMS M5 SEMS Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System Fixing System on a Wall Type A CPE Outdoor can be fixed on wall using a mounting bracket. This section details the procedures for fixing the mounting bracket on the wall and fixing the CPE Outdoor on the mounting bracket. To mark on the wall 1 Ensure that the items mentioned in below table are available. Table 5.
Confidential Chapter 2 Installing System Figure 14. CPE Outdoor Marking Dimensions for Wall Type 5.03 (127.75) Unit: in. (mm) : Anchor Bolt Hole 4.13 (105) [Rear View] 3 Place the mounting bracket on the fixing location, check the level status using a level, and adjust the level of the bracket assembly. 4 If the level status is normal, mark the anchor bolt holes on the wall. This is detailed in figure below. Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System Figure 15. Marking Wall Type Marking Point 5.03 (127.75) Unit: in. (mm)/ If it is level, the bubble of the spirit level is positioned at the center of both lines. 4.13 (105) To drill the anchor holes 1 Ensure that the items mentioned in below table are available. Table 6. Tools for Drilling Category Description Woking Tools Hammer Drill Drill Bit (1/4 inch) Vacuum Cleaner Table 7.
Confidential Chapter 2 Installing System Figure 16. Drilling Example Vacuum Cleaner 1/4 in. (6 mm) Hammer Drill To fix the Mounting Bracket on the wall 1 Ensure that the items mentioned in below table are available. Table 8.
Confidential Chapter 2 Installing System Figure 17. Fixing Mounting Bracket on the Wall (1) Wall Plastic Anchor 3 Place the mounting bracket along with the fixed plastic anchors. Figure 18. Fixing Mounting Bracket on the Wall (2) M4, L25, +, Taptite Screw Mounting Bracket When fixing the mounting bracket, be sure to fix it in the correct orientation. The imprinted angle mark must be on the top. Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System To fix the CPE Outdoor on the wall 1 Ensure that the items mentioned in below table are available. Table 9. Parts and Tools for Fixing CPE Outdoor on the Wall Category Description Parts Fastener Recommended Torque Value M5 SEMS Working Tools • Screw Driver Bit (+, No.2) • Torque Driver (2–10 lbf·in) M5 x L20 SEMS (CAPTIVE) 2 EA 4.4 lbfin (5.
Confidential Chapter 2 Installing System Figure 19. Fixing CPE Outdoor on the Wall Mounting Bracket Hook Groove of the Mounting Bracket M5 SEMS Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System System Tilting & Swiveling To tilt the system 1 Ensure that the items mentioned in below table are available. The description and the images in this section are based on the CPE Outdoor installed on a pole. However, you can also tilt and swivel the CPE Outdoor when it is installed on a wall just as like you can with one installed on a pole. Table 10.
Confidential Chapter 2 Installing System Figure 21. System Tilting (2) [UP Tilting] [Down Tilting] 4 Turn the screws (used to adjust the angle) on both sides of the mounting bracket assembly clockwise to fix the CPE Outdoor. Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System Figure 22. System Tilting (3) [Left View] [Right View] M5 SEMS To swivel the system 1 Ensure that the items mentioned in below table are available. Table 11. Tools for System Swivelling Category Description Recommended Torque Value M5 SEMS Working Tools • Screw Driver Bit (+, No.2) • Torque Driver (20–90 lbf·in) • Screw Driver (+, No.
Confidential Chapter 2 Installing System Figure 23. System Swivelling (1) [Top View] M5 SEMS [Bottom View] M5 SEMS 3 Adjust the swivelling angle by pulling the CPE Outdoor to the left or right. o Left swivelling: 5°/10°/15°/20°/25° o Right swivelling: 5°/10°/15°/20°/25° Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System Figure 24. System Swivelling (2) [Left Swivelling] [Right Swivelling] 4 Turn the screws (used to adjust the angle) on the top and bottom of the mounting bracket assembly clockwise to fix the CPE Outdoor. Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 2 Installing System Figure 25. System Swivelling (3) [Top View] M5 SEMS [Bottom View] M5 SEMS Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Chapter 3 Connecting Cables This chapter describes the procedures to connect cables to a CPE Outdoor system and to label the cables. Cabling Procedure Figure below depicts the procedure to connect system cables. Figure 26.
Confidential Chapter 3 Connecting Cables Guidelines for Cable Connections Figure below depicts the sequence of operations for connecting cables to the system. Figure 27. Cable Connection Procedure Cable Path Inspection Cable Cutting Cable Installation Connector Attachment When assembling the connector at the site Connector Assembly Cable Binding Identification Tag Attachment When cutting the cable after installation, ensure that the connector is disconnected.
Confidential Chapter 3 Connecting Cables • The cable must be placed in a location where the cable is not damaged by external factors such as power line, flooding, and footpaths. • In areas where the cable may be damaged by external factors, ensure that measures are taken to prevent damage to the cable, such as cable tray, ducts, and flexible pipe. Cable Cutting Measure the exact distance after carefully checking the route, and cut the cable using a cutting tool.
Confidential Chapter 3 Connecting Cables Table 12. Recommended Minimum Allowed Cable Bending Radius No Cable Allowed Cable Bending Radius 1 Ground/Power Cable • Operation: 8 × OD • Installation: 12 × OD 2 Ethernet Cable 4 × OD ※ If the allowed cable bending radius is specified by the manufacturer, comply with the bend radius specified. Cable Binding This process involves fixing and arranging an installed cable using binding thread, cable ties, binding wire, and ram clamps.
Confidential Chapter 3 Connecting Cables Identification Tag Attachment This process involves attaching a marker cable tie, a nameplate, and a label to both ends of a cable (connections to a connector) to identify the use of the cable and the cabling path. Follow these guidelines when attaching an identification tag. • When installing the cable outdoor, use relief engraving and coated labels to prevent the markings from being erased.
Confidential Chapter 3 Connecting Cables Cabling Diagram The cabling diagram of the system is as follows: Figure below depicts the cabling diagram of CPE Outdoor. Figure 28. Cable Diagram [Inside Building] [Outside Building] 2) AC Power Cable 4) Ethernet Cable-2 Home Router [CPE Outdoor Bottom] 1) Ground Cable MGB 3) Ethernet Cable-1 - [PoE Midspan] AC Outlet Table below lists the main specifications of the CPE Outdoor cable connections. Table 13.
Confidential Chapter 3 Connecting Cables Grounding Grounding is the process of operating an electronic system such as power supply system, communication system, and control system, stably without damage from lightning, transient-current, transient-voltage, and electric noise. Grounding also helps in preventing injury from electric shock. Ground equipment minimizes the electrical potential of the electronic device to that of the ground, which is zero electrical potential.
Confidential Chapter 3 Connecting Cables Category Description Fastener MGB Checking MGB specifications per site and preparing connecting parts CPE Outdoor M6 × L12 SEMS (Hex.
Confidential Chapter 3 Connecting Cables 4 Align the pressure terminal to the mounting hole of the CPE Outdoor ground terminal. 5 Firmly fix the pressure terminal onto the CPE Outdoor ground terminal using fasteners. Figure below depicts the steps 3 to 5. Figure 30. Connecting Ground Cable to the CPE Outdoor (2) M6 SEMS (Hex., +) Pressure Terminal Heat Shrink Tube (clear) Ground Cable Samsung 5G Station Outdoor Installation Manual v1.
Confidential Chapter 3 Connecting Cables Power Cabling Figure below depicts the elements of a power supply device. Figure 31. Power Equipment Elements AC Distributor (AC Outlet) 100–240 V AC PoE Midspan PoE CPE Outdoor Handling the power cable incorrectly may damage the rack or cause an electric short-circuit through the cable. Ensure the power switch of the rectifier or the system is turned off before handling the power.
Confidential Chapter 3 Connecting Cables 2 Install the AC power cable from the AC distributor to the PoE midspan, as shown in figure below. Figure 32. Connecting Power Cable to the PoE Midspan (1) [PoE Midspan] AC Power Cable AC Outlet 3 Insert the connector to the AC IN port of PoE midspan. Figure 33. Connecting Power Cable to the PoE Midspan (2) [PoE Midspan] AC IN Port AC Power Cable Assembly Samsung 5G Station Outdoor Installation Manual v1.
Confidential Chapter 3 Connecting Cables Interface Cable Connection This section describes the procedures to connect interface cables. Connecting Ethernet Cable [PoE Midspan] Ethernet Cable-1 Home Router Ethernet Cable-2 The Ethernet cable total length between home router, PoE midspan and CPE Outdoor should not exceed 100 m. The total length of Ethernet cable-1 and Ethernet cable-2 should not exceed 100 m. The Ethernet cable should be installed before installing the CPE Outdoor.
Confidential Chapter 3 Connecting Cables Changing Ethernet Cable from the CPE Outdoor To change an Ethernet Cable from the CPE Outdoor 1 Ensure that the items mentioned in below table are available. Table 16. Parts and Tools for Changing Ethernet Cable from the CPE Outdoor Category Description Installation Section CPE Outdoor LAN port Cable CAT6 SFTP Cable or higher, 23 AWG, 8.
Confidential Chapter 3 Connecting Cables 2 Unfasten a cable gland nut and separate a filler and plastic clip from cable gland body. Figure 34. Changing Ethernet Cable from the CPE Outdoor (1) [CPE Outdoor Front] [CPE Outdoor Front] Cable Gland Body Filler Plastic Clip Cable Gland Nut 3 Remove the RJ-45 plug from the system side’s LAN port. Press the latch with the fingers, remove the cable from the connector. Figure 35.
Confidential Chapter 3 Connecting Cables 4 Separate the filler, plastic clip and cable gland nut in order from the Ethernet cable. Figure 36. Changing Ethernet Cable from the CPE Outdoor (3) Plastic Clip Cable Gland Nut Filler Ethernet Cable Samsung 5G Station Outdoor Installation Manual v1.
Confidential Chapter 3 Connecting Cables 5 Insert the cable gland nut, plastic clip and filler nut in order to the new Ethernet cable. Figure 37. Changing Ethernet Cable from the CPE Outdoor (4) Plastic Clip Cable Gland Nut Filler New Ethernet Cable 6 Insert the RJ-45 plug to the system side’s LAN port. (At this time the latch of cable side connector should be toward to the rear side.) Figure 38.
Confidential Chapter 3 Connecting Cables 7 Push the filler and plastic clip to the cable gland body and connect the cable gland nut. Figure 39. Changing Ethernet Cable from the CPE Outdoor (6) [CPE Outdoor Front] [CPE Outdoor Front] Filler Plastic Clip Cable Gland Nut Connecting Ethernet Cable to the PoE Midspan To connect an Ethernet Cable to the PoE Midspan 1 Ensure that the items mentioned in below table are available. Table 18.
Confidential Chapter 3 Connecting Cables Table 19. Ethernet Cable Pin Map (PoE Midspan ~ Home Router) PoE Midspan Color Map Home Router Function 1 White/Orange 1 BI_DA+ 2 Orange 2 BI_DA- 3 White/Green 3 BI_DB+ 4 Blue 4 BI_DC+ 5 White/Blue 5 BI_DC- 6 Green 6 BI_DB- 7 White/Brown 7 BI_DD+ 8 Brown 8 BI_DD- 2 Connect an Ethernet cable from CPE Outdoor to PoE midspan. Figure 40.
Confidential Chapter 3 Connecting Cables Figure 42. Connecting Ethernet Cable to the PoE Midspan (3) [PoE Midspan] Home Router Ethernet Cable 5 Connect the RJ-45 latch of Ethernet cable to PoE Midspan IN port. Figure 43. Connecting Ethernet Cable to the PoE Midspan (4) [PoE Midspan] IN Port To check a LED 1 After turning the power on CPE Outdoor, check the status of LED. Table 20.
Confidential Chapter 3 Connecting Cables Process Status Regular mode Internet available (app confirms 5G signal test is done) Solid Cyan dimmed to 50 % brightness Internet disabled through device settings Yellow blinking (600 ms ON, 600 ms OFF) until Internet's available BT connection success Cyan blinking (200 ms ON, 200 ms OFF) x 3 BT connection failure Red blinking (200 ms ON, 200 ms OFF) x3 Changing from installation mode to regular mode (press RESET key for 3 seconds) Cyan blinking (200 ms
Confidential Chapter 3 Connecting Cables Figure 44. Checking a LED (1) LED Cover - After turning on the CPE Outdoor, connect an auxiliary battery. It will operate in installation mode, and you can check the 5G signal strength with the LED. If there is nothing wrong, disconnect the auxiliary battery and connect the cable. - After completing the installation, use the RESET key to switch from installation mode to regular mode.
Confidential Chapter 3 Connecting Cables Figure 45. Checking a LED (2) Samsung 5G Station Outdoor Installation Manual v1.
Confidential Chapter 4 Inspect the Installation Chapter 4 Inspect the Installation This chapter describes the procedures to check installation status. Figure below depicts the overall procedure for inspecting the installation status. Figure 46.
Confidential Chapter 4 Inspect the Installation On-site Inspection and Inspection Checklist The on-site inspection is to perform inspection visually or using instruments for each specification, standard, and installation status, based on the inspection checklist at the site where the system is installed. The inspector must record the results onto the inspection checklist during or after field inspection.
Confidential Chapter 4 Inspect the Installation Category Check Items Criteria Result Pass Cabling Fail Cable damage Proper installation route Compliance with the radius of curvature Cable binding status Binding status Binding interval Checking binding materials Cable connection Assembly condition of a pressure terminal Fastening condition of a pressure terminal Checking compliance with fastening torque value Power Cable specification Checking the specification Checking the limit distance Cabli
Confidential Appendix A Acronyms AC CPE DC EMC MGB PoE RTN SEMS SIM UTP Alternating Current Customer Premises Equipment Direct Current Electromagnetic Compatibility Main Ground Bar Power over Ethernet Return pre-asSEMbled washers and screws Subscriber Identity Module Unshielded Twisted Pair Samsung 5G Station Outdoor Installation Manual v1.0 Copyright © 2020, All Rights Reserved.
Confidential Appendix B Standard Torque When operator fastens the bolt, use the standard torque values provided in tables below to prevent the equipment and bolt from damage and secure by fastening. When the torque value for each connection part is defined already, use the defined value. Table 23. Standard Torque Value for Fastening Bolts Bolt Spec. Torque Value (N·m) Torque Value (lbf·in) Torque Value (kgf·cm) M3 0.63 5.6 6.4 M4 1.5 13 15 M5 2.8 25 29 M6 4.
Samsung 5G Station Outdoor Installation Manual Document Version 1.0 © 2020 Samsung Electronics Co., Ltd. All rights reserved.