User's Manual

Table Of Contents
Samsung CDMA BSS: Indoor BTS Installation Manual
11
BSS Version 4, Document V4D0001 release 0.5, Indoor BTS Installation
Manual, release 2.0
Unpacking and moving the rack
Unpacking the rack Note: Unpack racks one at a time. Do not unpack any crates until
you are ready to use their contents.
Note: Samsung equipment is packed in wooden crates with foam
inserts to protect equipment. Remove the crate from the equipment.
Do not attempt to remove the equipment from the crate.
Note: Retain packing materials safely until you have completed
installing all the equipment.
Note: Verify the width and height of the entry doors and corridor for
sufficient space for easy movement. Take special care not to
damage or destroy the entry, wall or installation site.
Use the following procedure to unpack each rack:
1 Locate and inspect the crate containing the rack. If the crate is
damaged, notify the shipper.
2 Remove the metal straps from around the crate.
3 Remove the lid from the crate.
4 Remove the packing foam from inside the crate.
5 Cut open the plastic film surrounding the rack, and fold it back over
the sides of the crate.
6 Stand the rack upright: one person should stand in front of the box to
ensure that the unit does not tip over once it is upright.
7 “Walk” the rack out of the box. It is more effective if one person holds
the crate, and another the rack.
Caution: Racks weigh up to 400 kg. (882 lb.). If using a dolly to
transport the rack, Samsung recommends two people tilt and hold
the rack while a third person places the dolly.
Lifting provisions After unpacking the rack, use the following procedure to lift
the rack if it is to be lifted to a location higher than the first
floor.
All personnel participating in this procedure must be
certified and follow the requirements of OSHA, FCC, and ANSI
standards. The operator in charge of lifting the equipment may
at his choice select the method to lift the equipment. The
following procedure is one method for lifting the equipment:
Each rack is equipped with eyebolts on its top surface when it is
delivered. After unpacking the rack, use the following procedure to
lift the rack:
1 Before the lift begins, the lift operator and personnel should
familiarize themselves with the installation location.