CHAPTER 2. Installation
2-24 © SAMSUNG Electronics Co., Ltd.
2.4 Equipment Installation
The procedure for installing equipment ahead of earth is as follows:
1) Carrying and Unpacking Equipment
2) Rack Installation
3) Circuit Pack Treatment
4) Equipment Arrangement
5) Cabling
2.4.1 Carrying and Unpacking Equipment
The operator should check if proper materials and goods are brought and if their quantities
are correct according to the installation plan. AC power cables, DC power cables, switches,
and conduit tubes should be selected for installing the system and lighting according to
each standard. The operator should notify the workers movement in advance so that the
workers can be allowed to go in and out the target office freely. In addition, the operator
should discuss with departments of implementation and operation for an existing
communication system and interface.
2.4.1.1 Equipment Delivery Rule
Permissible shock level while equipment such as racks and materials is moved is as
follows:
Packed Rack
Weight(kg) Falling Height(mm)
Less than 450 300
Unpacked Materials
Weight(kg) Falling Height(mm)
0~10 100
10~25 75
25~50 50
50 or More 25