MPI: GE, 240v, Single Phase, Remanufacturing Process
97-xxxx, Rev:A Page 9 of 13
7.1.2 Use the needlenose pliers to grip the AC cable fast-on connector, then press it fully onto
the fast-on tab on the BAMM/BAMMCCSK. Repeat for the other cable.
Note: Do not attempt to straighten a BAMM/BAMMCCSK fast-on tab that is bent. If the
fast-on connector cannot be fully seated onto the tab because the tab is bent too
much, reject the BAMM/BAMMCCSK.
8. Interrupter Installation
8.1 Insert the interrupter into the interrupter installation tool as shown below. It is important
that the interrupter and the interrupter tool are properly oriented.
Handle the interrupter from long side of hub not the interrupter blades. Do
not touch the interrupter blades as you insert the interrupter into the tool.
Figure 3: Interrupter Installation
8.2 Carefully position the interrupter next to and parallel to the meter shaft with the spacer
side 2of the tool resting totally flush on the bottom of the meter disk. Use your finger or
thumb to press the tool totally flush against the disk when you snap the interrupter onto
the disk.
8.3 Verify that the installation tool is held perfectly vertical, then gently squeeze the pliers until
the interrupter snaps onto the meter shaft. If you dont feel or hear the snap, the
interrupter might be damaged or in the wrong position.
interrupter
letter G
on this side
long side
of hub
meter disk
finger pressure