26 HEATING CABLE TESTS LOG
Each heating cable is subject to factory quality control. However, damage to the cables may happen after the product leaves the factory.
In order to ensure that the cable quality remains unchanged throughout the installation process and for warranty purposes, tests must be
conducted while the cable is still on the spool and during two specific subsequent steps. Measurements must be recorded in the table below
and compared to initial measurements taken when the cable was on the spool in order to enable you to detect any changes related to the
electrical property of the cable. Any installation-related cable damages are not covered by the warranty.
Homeowner/end user must retain this heating cable tests log for warranty purposes.
HEATING CABLE TESTS LOG
Validation for warranty coverage
Heating Cable Tests Log
Project: ___________________________________________________________ Date of installation: ___________________________
Certified electrician: _______________________________________________ Date of start-up: ______________________________
Identification Factory Value Before Installation After Cable Installation After Tile Installation
Conductor Resistance Test
Conductor and Ground Braid Continuity Test
Infinity (I) or
Overload (OL)
Insulation Resistance Test
Equal to or
greater than
1 Gigaohms*
Floor Temperature Sensors Test
Temperature Resistance
ºC ºF Kohms
10 50 18.1
15 59 14.8
20 68 12.1
25 77 10.0
30 86 8.3
*1 Gigaohms = 1 G ohms = 1000 M ohms = 1000 Mega ohms