Waterproofing
At the joints, fill the matting with Schluter
SET
®
, Schluter ALL-SET
®
, Schluter FAST-
SET
®
, or unmodified thin-set mortar,
approximately 8" (203 mm) wide, centered
over the joint.
1
Comb additional Schluter SET
®
,
Schluter ALL-SET
®
, Schluter FAST-
SET
®
, or unmodified thin-set mortar
over the joint using a 1/4" x 3/16"
(6 mm x 5 mm) V-notched trowel or the
KERDI-TROWEL, which features a 1/8" x
1/8" (3 mm x 3 mm) square-notched design.
2
Apply 5" (127 mm)-wide KERDI-BAND,
centered over the joint. Using the flat side
of the trowel, firmly press the banding into
the mortar to ensure 100% coverage and to
remove excess mortar and air pockets.
3
At all wall junctions, apply KERDI-BAND as
described in steps 1-3, centered where the
wall and floor meet. In some applications
the vertical section of the floor/wall transition
will not accept a bond to unmodified
thin-set mortar. Connections to such
elements can be achieved using KERDI-FIX
sealant and bonding compound or suitable
trowel-applied waterproofing materials, such
as those that require atmospheric moisture
to cure (e.g., urethane sealant).
4
Note: KERDI-BAND must lap DITRA-HEAT and DITRA-HEAT-DUO at seams and at floor/wall
transitions by a minimum of 2" (50 mm) in order to maintain waterproof integrity.
The following steps are required for waterproofing only:
Note: While the heating cable is protected by the DITRA-HEAT and DITRA-HEAT-DUO matting, be careful when applying the mortar to not
damage the cable with the notched trowel.