Schneider Conext SW AC Stacking Kit

975-0682-01-01 REV C
Copyright © 2013 Schneider Electric. All Rights Reserved. All trademarks are owned by Schneider Electric Industries SAS or its affiliated companies.
For use by qualified personnel only.
Page 1 of 2
Conext
TM
SW AC Stacking Kit 120/240V (865-1019)
Installation Guide
Contact Information
www.schneider-electric.com
Please contact your local Schneider Electric Sales Representative or visit the Schneider Electric website at:
http://www.schneider-electric.com/sites/corporate/en/support/operations/local-operations/local-operations.page
Important Safety Instructions
READ AND SAVE THESE INSTRUCTIONS - DO NOT DISCARD
Installation (see corresponding diagrams)
Detach the switchgear cover.
Remove the breaker knockouts as shown on the diagram to make room for the additional AC breakers
and re-label the panel identifying the new breaker positions.
Do not remove the last two breaker knockouts.
In the main switchgear cabinet, remove all wires connected to all the breakers including the jumper
bars and the handle interlock device.
Loosen the leftmost 30A breaker and the center 60A breaker and distribute them evenly to the left
along the rail to make room for the additional AC breakers.
Install the additional AC breakers. The two breakers in the middle must be the 60A breakers.
Install the jumper bars (four-finger) and wire the additional AC breakers. Connect additional neutral
and ground wires to their respective busses. Use only qualified personnel to ensure compliance with all
applicable installation and electrical codes and regulations.
Replace the AC switchgear cover. Secure the cover using the same screws that came with the product.
Install the Interlock plate. First, insert the bottom flange of the interlock plate into the slots in the switch-
gear cover. Then secure the top of the interlock plate with the two screws (provided).
Conext SW AC Switchgear
(865-1017)
Materials List
The Conext SW AC Stacking Kit (865-1019) ships with the following items:
1x
2x
1x
2x
1x
1x
6x
2x
1x
1x
Installation Guide
Double-pole 30A AC Breaker
Double-pole 60A AC Breaker
Jumper Bars (four-finger)
Interlock plate with two screws
Breaker label sticker
10AWG AC Wire (black)
10AWG AC Wire (red)
10AWG AC Neutral Wire (white)
10AWG AC Ground Wire (green)
REMOVE
KEEP
PLACE LABEL
UNSCREW
REMOVE
JUMPER BARS
REMOVE
INTERLOCK
REMOVE
WIRES
REMOVE
WIRES
AC OUT BYPASS AC IN
ELECTRIC SHOCK, EXPLOSION, AND ARC FLASH HAZARD
Failure to follow these instructions will result in death or serious injury.
All wiring must be done by qualified personnel to ensure compliance with all applicable installation codes and
regulations. Refer to the Conext SW inverter/charger Installation Guide for a definition of qualified personnel.
Disconnect and lockout all DC and AC sources that are powering this equipment and any connected equipment
before installing, servicing, and performing any upgrades.
Always wear proper personal protective equipment (PPE) before working on or inside this equipment.
Always use a properly rated voltage sensing device to check the presence of potential and residual energy.
DANGER
NOTE: The lengths of the supplied wires are long enough for when the AC switchgear is installed
below the inverters and the inverters are stacked vertically in one line. Longer wires are required
when the AC switchgear is installed above the inverters. Use and cut appropriate wires with the
same gauge and termination as the supplied wires.