Installation Guide

NOTICE
CHARGE CONTROLLER DAMAGE
The charge controller can overheat if installed in a sealed, indoor enclosure. Do not install
the charge controller in a sealed compartment.
Failure to follow these instructions can result in equipment damage.
To help ensure optimal and safe operation, make sure there is adequate clearance around
the charge controller. See Table 1 and Figure 2. If clearances are reduced below these
minimums, charging performance might be impaired.
Location Minimum Clearance
Above
and below
6 inches (150 mm). Do not mount charge controllers in a vertical
stack.
In front
Sufficient room to allow for easy access to see the LEDs and to
perform maintenance.
Sides
No clearance requirement. One charge controller can be mounted
on the side of the Conext Power Distribution Panel (PDP) (Part
Number 865-1015-01). For more information, see the Conext XW+
or Conext XW Pro Inverter/Charger Installation Guide. Other
installations must follow the guidelines in this Guide.
Table 1Minimum clearance requirements
Figure 2Minimum Clearance Requirements
Conext MPPT 80 and MPPT 100 Installation Guide Installation
25 This document is for use by qualified personnel 990-91319B