Conext SW 4024-120 Install Guide

Table Of Contents
Installation
1–18 975-0639-01-03
This guide for use by qualified personnel only
Inverter/Charger Installation
Overview
This section provides detailed information on installing the Conext SW. The
overall procedure is divided into seven steps:
Step 1: Choosing a Location for the Inverter/Charger on page 1–19
Step 2: Mounting the Inverter/Charger on page 1–20
Step 3: Connecting the AC Input and AC Output Wires on page 1–22
Step 4: Installing the DC Switchgear and Connecting the DC Cables on page 1–25
Step 5: Connecting the BTS and Xanbus-enabled Components on page 1–29
Step 6: Performing Checks Prior to Initial Start-Up on page 1–31
Step 7: Testing Your Installation on page 1–31