Schneider Electric User Guide

Charger Settings Menu
975-0240-01-01 3–13
Multi-Stage Charging Process
The charging cycle is a multi-stage process. Whenever qualified AC power is
present at the AC1 or AC2 input, power runs through to the connected load and
begins charging the batteries in parallel.
NOTES:
When the charge cycle is interrupted, the charger will restart charging at the
beginning of the multi-stage algorithm.
Note: Using the Conext SCP, make sure that every XW+ unit in the multi-unit
configuration is set to Charger = Enabled under the Setup menu for each
inverter.
Note: If Cascading is Enabled in SCP, the charger settings will cascade to
other Conext XW+ units with the same DC Associations. However, they will not
cascade to other device types such as MPPT solar charge controllers and the
Battery Monitor even if they have the same DC associations. Make sure that the
charger settings are configured correctly on the other device types.
Figure 3-4 Three-Stage Battery Charging Cycle
Time
Time
Absorption Voltage
Float Voltage
Max Absorb Time - Default
3
hrs
(adjustable 1 min - 8 hrs)
Boost
Timer
1hr fixed
Absorption Exit Current
Threshold = 2% of
programmed AH capacity
3-Stage Charge
Custom Charge
Float StageAbsorption Stage
Bulk Stage
(Boost Stage)
Battery
Current
Max Charge
Rate
Battery
Voltage
Conext XW+ Owner's Guide NA (975-0240-01-01).book Page 13 Monday, November 27, 2017 10:00 AM