Conext XW+ 230V Installation Guide

Table Of Contents
Wiring the Conext XW+ Inverter/Charger without a PDP
975-0714-01-01 3–13
This manual is for use by qualified personnel only
To connect DC cables to the Conext XW+ Inverter/Charger (without a PDP):
1. Route the DC cables through your chosen knockouts on the Conext XW+
Inverter/Charger.
2. Install a Conext Battery Fuse Disconnect Box (see “Optional Accessories” on
page 1–4) between the Conext XW+ Inverter/Charger and the battery, as
close to the battery as possible. (For detailed installation instructions, consult
the documentation included with the Battery Fuse Disconnect Box.)
3. Connect the POSITIVE (+) cable to the POSITIVE DC terminal on the first
inverter/charger (INV1).See Figure 3-8, “DC Connections to a Single Inverter
without a PDP” on page 3–14.
Be sure to observe proper polarity. See Figure 3-7 (above) for the proper
stacking order of hardware.
4. Tighten the bolt to the required torque. (See “Torque Values” on page 2–16.)
5. Connect the other end of the POSITIVE (+) cable to the Conext Battery Fuse
Disconnect Box. (For detailed instructions, consult the documentation
included with the Battery Fuse Disconnect Box.)
6. Connect the NEGATIVE (–) battery cable to the NEGATIVE (–) DC terminal on
INV1. Be careful to observe proper polarity. See Figure 3-7 (above) for the
proper stacking order of hardware.
7. Tighten the bolt to the required torque. (See “Torque Values” on page 2–16.)
8. Connect the other end of the cable to the Conext Battery Fuse Disconnect
Box. (For detailed instructions, consult the documentation included with the
Battery Fuse Disconnect Box.)
9. Tighten the bolt to the required torque. (See “Torque Values” on page 2–16.)
10. Attach the DC terminal covers.
11. Repeat steps 3 through 10 for the second and third inverter/chargers (INV2
and INV3), as necessary. See Figure 3-9, “DC Connections for a Dual
Inverter System without a PDP” on page 3–15 and Figure 3-10, “DC
Connections for a Triple Inverter System without a PDP” on page 3–16.
Note: For dual and triple inverter installations, you will need to install two Conext
Battery Fuse Disconnect Boxes.