Conext XW+ 230V Installation Guide

Table Of Contents
Wiring the Conext XW+ Inverter/Charger with a PDP
975-0714-01-01 3–51
This manual is for use by qualified personnel only
5. Repeat steps 1 through 4 for INV2 and INV3, as necessary.
6. Connect the LOADS breaker(s) to the AC LOADS panel.
7. Connect the GRID breaker to the utility grid distribution panel.
8. If the installation includes a generator or second AC source, connect the L
AC wiring from each pole on the GEN breaker to the corresponding AC Input
(AC2) terminal on each Conext XW+ unit.
9. Using the labels included with the PDP, re-label the AC breakers, as
appropriate.
10. Install a bypass interlock plate or external bypass switch, as appropriate. For
more information, contact your contact your local Schneider Electric Sales
Representative.
Figure 3-26 Inverter/Charger Three-Phase AC Wiring
Note: Neutral inputs are connected to each other, requiring only one neutral
connection when installed with a Conext XW+ Power Distribution Panel. Without
the PDP, additional neutral connections may be required at the input sources
AC1
AC2
Event
Equalize
kW
A
Charging
!
Inverting
AC INAC OUT AC IN
GRID
(AC1)
AC
LOAD
GEN
(AC2)
NLNLNL
GEN Breaker
GRID Breaker
LOADS Breaker
Connect INV2 and INV3 the
same way