Installation Guide

Table Of Contents
Wiring the Conext XW+ Inverter/Charger and Conext XW+ Power Distribution Panel
3–20 975-0239-01-01 Rev G
This manual is for use by qualified personnel only
AC Equipment Grounding
See Table 2-4 on page 2–16 for torque values for the AC terminal and AC ground
bar. See Table 2-8 on page 2–16 for torque requirements for the ground bar in
the Conext XW+ Power Distribution Panel.
Figure 3-11 AC Equipment Grounding With the PDP
AC INAC OU T AC IN
GRID
(AC1)
AC
LOAD
GEN
(AC2)
NL1L2NL1L2NL1 L2
4
1
2
5
3
L1L2
NG
L1 L2
1. To AC ground bar
2. To main utility panel
3. To inverter load sub-panel
Note: May not be required if DC ground is used
instead.
4. Generator disconnect
Note: Depending on the location of the generator
and local code requirements, the generator
disconnect may be located in the power
distribution panel.
5. To AC generator
Grounding requirements may vary.
Cable routing may vary. See Knockout Selection
on page 2-5 and Communications Network
Preparation on page 2-12. For torque values, see
page 2-16 and 2-17.
LEGEND