Installation Guide
Table Of Contents
- Conext™ XW+ Inverter/Charger Installation Guide
- Conext™ XW+ Inverter/Charger Installation Guide
- About This Guide
- Important Safety Instructions
- Contents
- Introduction
- Overview
- Optional Accessories
- Conext XW+ Conduit Box
- Conext XW+ Power Distribution Panel
- Conext XW+ Connection Kit for INV2 INV3 PDP
- Conext 120/240VAC Breaker Kit for Conext XW+ PDP
- Conext MPPT 60 150 Solar Charge Controller
- Conext MPPT 80 600 Solar Charge Controller
- Conext System Control Panel
- Conext Automatic Generator Start
- Conext ComBox
- Conext Battery Monitor
- Conext 3 Phase Breaker Kit for Conext XW+ PDP
- 100A, 125VDC Breaker Master Pack (12 units)
- 80A, 125VDC Breaker Master Pack (12 units)
- 60A, 160VDC Breaker Master Pack (48 units)
- 250A, 160VDC Breaker Master Pack (6 units)
- Pre-Installation and Wall-Mounting
- Wiring the Conext XW+ Inverter/ Charger and Conext XW+ Power Distribution Panel
- Removing the AC Access Panel and PDP Internal Faceplates
- Communication Ports and BTS Port
- Wiring the Conext XW+ Inverter/Charger with a PDP
- Basic Functional Test – Single Inverter
- Wiring Additional Conext XW+ units with a PDP
- Basic Functional Test - Multiple Inverters
- Wiring a Balanced Three-Phase System
- Wiring the Conext XW+ Inverter/Charger without a PDP
- Xanbus Network Installation
- Conext XW+ Inverter/Charger Accessories Installation
- Specifications
- Wiring Diagrams
- Split-Phase to Single-Phase Conversion Instructions
Basic Functional Test – Single Inverter
975-0239-01-01 Rev G 3–33
This manual is for use by qualified personnel only
To disable the inverter:
◆ On the inverter information panel, simultaneously press the STARTUP/
SHUTDOWN button and the Equalize button. The Conext XW+ is now disabled,
and (disabled) is briefly displayed on the inverter information panel,
followed by "" (as shown in Figure 3-19).
3. Monitor the invert (green kW) LED to confirm which mode the inverter is in:
•kWLED OFF – Invert mode is disabled. The inverter/charger is not
powering the AC loads. However, if good AC is present, it is passed
through to the loads.
• displayed on the inverter information panel – The inverter/charger is
in search mode and is looking for an AC load greater than the Search
Watts setting (default = 25 watts). The display shows
(Search)
when this mode has been enabled.
• LED ON – The inverter/charger is on. The inverter is operating and is
able to provide power to the AC loads. This is the default mode on initial
power-up once the unit is taken out of standby mode.
If the inverter is not operating or the inverter LED (kW) does not turn on, check all
connections. Check the inverter’s DC voltage and polarity on the positive (+) and
negative (–) terminals. Check the Fault LED. If the fault LED is on, check for a fault
Figure 3-19 Transition to disabled mode