Verification
4–4 975-0581-01-01
This manual is for use by qualified personnel only
Corrective Action
Perform after initial inspection (if required):
1. Take minor corrective actions as per instructions outlined in the previous
paragraphs. For more significant corrective actions, contact Schneider
Electric customer service.
2. Ensure that the AC and DC disconnect switches, as well as any utility
interconnect circuit breaker, main disconnect circuit breaker and/or AC
control power disconnect are left locked-out and tagged-out.
3. Close and latch the doors of the inverter enclosure, the AC and DC interface
enclosures.
4. Inform Schneider Electric’s customer service regarding corrective actions
taken (provide details, take photos prior and after the repair) and seek
permission from Schneider Electric to engage the unit.
Energize Procedure (Startup)
To start up the Xantrex inverter:
1. Ensure nobody is working on any circuits in the system, and that the inverter
cabinet and all other enclosures are closed and secured.
2. Remove any lockout devices from the utility connection circuit breaker and
DC disconnect switch.
3. Remove any lockout devices from the auxiliary control power disconnect and
energize the auxiliary control power.
4. Close the utility connection circuit breaker.
5. Close the AC disconnect switch.
6. Verify the
E-STOP pushbutton is in the CLOSED (extended) position.
7. If a remote E-STOP is installed, verify it is in the CLOSED position.
8. Turn the 3 (stand-by/power-on) switch (called
ON/OFF on older models) to
the 2 (power-on) position.
After a 15 second initialization period, the Xantrex inverter automatically
transitions to ‘Waking Up’, given the PV voltage is greater than the PV V Start set
point.