Mounting and Anchoring the Units
152364 3–5
This manual is for use by qualified personnel only.
Mounting and Anchoring the Units
To mount and anchor the Xantrex GT100 E:
1. Predrill the floor or pad to accept masonry anchors for 12 mm bolts, or
ensure it has pre-installed anchoring bolts that will fit the 18 mm mounting
holes. See Figure 2-3 on page 2–7.
2. Lift the Xantrex GT100 E from beneath with a forklift or pallet jack as shown in
Figure 3-2 on page 3–3, or lift the Xantrex GT100 E from above as shown in
Figure 3-3 on page 3–4. Move the inverter enclosure into place.
3. Secure the inverter enclosure feet to the floor with the appropriate anchoring
hardware.
Figure 3-4 Mounting Locations
Mounting Hole