Xantrex GT100 E Connections
152364 3–11
This manual is for use by qualified personnel only.
AC Line Connections
To connect the AC line:
1. Route the line AC (A, B, C and N) cables through the base access panel.
2. Connect the cables to terminals on the AC disconnect switch respectively,
see Figure 3-8.
3. Secure the AC line cables to the tie wrap mounting terminals using
appropriate tie wraps.
Ground Connections
To connect the ground:
1. Install a copper ground rod within 1 meter of the Xantrex GT100 E enclosure.
Connect a ground cable to the ground rod.
2. Route the ground cable through the base access panel and connect the
cable to the ground terminal block TB1, see Figure 3-8.
Figure 3-8 Line Cable Routing
Ground Bar (TB1)
AC Line (N)
AC Line (C)
AC Line (B)
AC Line (A)