Verification and Commissioning
4–4 152364
This manual is for use by qualified personnel only.
Commissioning Procedure
This section provides the procedure necessary to safely and correctly
commission a Xantrex GT100 E inverter.
To commission the Xantrex GT100 E:
1. Ensure the system verification tests have been completed and have passed
successfully.
2. Begin the Xantrex GT100 E commissioning procedure as described in detail
further in this section. The steps are summarized below.
a) Record the serial number.
b) Inspect Xantrex GT100 E inverter enclosure.
c) Verify AC and DC voltages.
d) Apply grid voltage.
e) Check the front panel display.
f) Confirm operational parameters (AC, DC and power tracker).
g) Apply DC voltage.
h) Perform the matrix test.
i) Operate inverter.
3. Submit the commissioning test record and fax a copy of the product
registration form to Schneider Electric. Both forms are in the Warranty section
of the Xantrex GT100 E 100 kW Grid-Tied Photovoltaic Inverter Operation
and Maintenance Manual (Part # 152365).
Important: It is important to record any issues encountered while following this
procedure.