Installation manual

Table Of Contents
Starting the Commissioning Test
152364 4–7
This manual is for use by qualified personnel only.
7. Check all the operating data with the GUI or front panel. Record any
irregularities.
8. Let the inverter run.
9. Verify the matrix fans operate after the matrix temperature reaches at least
30°C, and the "INV kW" is at least 30 kW.
To complete the commissioning:
1. Once you have successfully completed all the commissioning steps, ensure
all the information is documented.
2. Fax a copy of the product registration form to Schneider Electric. The form is
in the Warranty section of the Xantrex GT100 E 100 kW Grid-Tied
Photovoltaic Inverter Operation and Maintenance Manual (Part # 152365).