Commissioning Test Record
Step 1. Record and Document Serial Number and Inverter Location
Date and Time of Commissioning:
Inverter Serial Number: Technician Name:
CCU2 Board Serial Number: Company Name:
Inverter Location: Bldg. # Contact Email:
Address: City: State:
Step 2. Installation and Cable Check
Power Conductors installed correctly: Yes
Terminations are properly torqued: Yes
Step 3. Verify AC Utility Voltage at CB1
A-B Measurement: B-C Measurement:
C-A Measurement: Phase Rotation: CW
Step 4. Verify DC PV Voltage at PV Contactor - K2
Pos - Neg Measurement: _________Vdc.
DC Polarity is correct: Yes
Step 5. Apply AC Grid Voltage to the Xantrex GT100 E
Control Power circuits energized: Yes
Notes:
Step 6. Confirm Operation of Universal Frontpanel Control Unit
User Interface Boots and Displays correctly: Yes
Software version (CCU2 SW): Software version (UFCU SW):
Notes:
Step 7. Confirm Write Menu Parameters for AC Limits
Max AC Volts %: Min AC Volts %:
Max AC Frequency: Min AC Frequency:
Max GND Fault:
Notes:
Step 8. Confirm Write Menu Parameters for PV Settings
PV V Start: PV T Start:
PV P Stop: PV T Stop:
Notes:
Step 9. Confirm Write Menu Parameters for Power Tracker Configuration
PPT V Ref: I PPT Max %:
PPT Enable: PPT Rate:
PPT V Rate:
Notes:
Step 10. Operate the Xantrex GT100 E in Power Tracking Mode
I PPT Max% initially set to10 %: Yes
I PPT Max % gradually increased to 100 %: Yes
Xantrex GT100 E operates correctly: Yes
Notes: