Installation manual
Commissioning
5–2 153396 Revision D
This manual is for use by qualified installers only
Commissioning Procedure
This section provides the procedure necessary to safely and correctly
commission a Xantrex GT250 inverter.
Summary To commission the Xantrex GT250:
1. Ensure the verification tests in Chapter 4, “Verification” have been completed
and have passed successfully.
2. Begin the Xantrex GT250 Commissioning Procedure as described in detail
further in this section. The steps are summarized below.
a) Record the serial number.
b) Inspect the Xantrex GT250 inverter enclosure.
c) Verify AC and DC voltages.
d) Apply grid voltage.
e) Check the front panel display.
f) Confirm operational parameters (AC, DC and power tracker).
g) Apply DC voltage.
h) Perform the matrix test.
i) Operate inverter.
3. Email completed Commissioning Test Record to
re.field-service@us.schneider-electric.com or mail to:
Xantrex Technology Inc.
161-G South Vasco Road
Livermore, CA
USA
Attention: Customer Service
Important: It is important to record any issues encountered while following
this procedure.
Important: Any Xantrex warranty obligation is conditional upon (a) the
commissioning of the Xantrex GT250 inverter in accordance with the
Commissioning Procedure set forth in detail in this section and (b) the return to
Xantrex of the fully completed Commissioning Test Record (see page B-3 of
Appendix B in this manual) promptly but no later than 30 days after the
completion of the commissioning. If a third party (hereinafter, an "integrator")
commissions the Xantrex GT250 inverter on behalf of an end user of such
inverter and such integrator fails to fully complete and timely return a
Commissioning Test Record, then Xantrex shall have the right to fulfill such end
user's warranty claims and recover from such integrator all costs and expenses
incurred by Xantrex in connection with such warranty claims.