Installation manual
Commissioning
5–6 153396 Revision D
This manual is for use by qualified installers only
Revised Protection Settings (If Required)
1. If default protection settings will be changed as authorized by the utility,
follow the W
RITE menu procedure documented in the Xantrex GT250 Grid-
Tied Photovoltaic Inverter Planning and Installation Manual.
2. Access the WRITE menu again by pressing
MENU but do not enter the
password.
3. Verify all protection settings are correct.
4. Press
MENU again to return to the standard menu.
Completed Commissioning
1. Once you have successfully completed all the commissioning steps, save
the test report to a file.
2. Email the completed Commissioning Test Record to
re.field-service@us.schneider-electric.com or mail to:
Xantrex Technology Inc.
161-G South Vasco Road
Livermore, CA
USA
Attention: Customer Service
Important:
Failure to return the fully completed Commissioning Test Record to
Xantrex within 30 days after the completion of the commissioning may result in the
delay of warranty claim service or loss of warranty coverage for the Product. If a
third party (hereinafter, an "integrator") commissions a Xantrex GT250 inverter on
behalf of an end user of such inverter and such integrator fails to fully complete
and timely return the Commissioning Test Record, then Xantrex shall have the right
to fulfill such end user's warranty claims and recover from such integrator all costs
and expenses incurred by Xantrex in connection with such warranty claims.