Installation Guide
2
www.SEsolar.com
Copyright © 2019 Schneider Electric. All Rights Reserved.
All trademarks are owned by Schneider Electric Industries SAS or its affiliated companies.
D5
Wiring – Conext™ Battery Monitor
D4 Wiring – Conext™ Mini Power Distribution Panel (PDP)
E Commissioning
F Specifications
D3 Installation – Cable Gland Installation
D2 Installation – Lock-out and Tag-out
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
• Do not connect this equipment to a live power source prior to cabling and wiring. This equipment
can be energized from two sources: DC from the battery, and AC from the grid.
• Do not connect any powered device to this equipment during installation.
Failure to follow these instructions will result in death or serious injury.
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
• This equipment must be installed only by qualified personnel and serviced only by authorized service
personnel equipped with appropriate PPE and following safe electrical work practices.
• Before opening any doors or covers:
- Consult the system diagram to identify all power sources. This equipment is energized from multiple
sources –
DC from the battery, and AC from the grid
.
- De-energize, lock out, and tag out all power sources. External disconnecting means for the DC and
AC sources, capable of being locked-out and tagged-out, must be provided as part of the installa-
tion. External disconnect devices are located elsewhere in the installation; they are not part of this
equipment.
- Wait at least ten minutes for internal capacitors to discharge to safe voltages; Wearing appropriate
PPE, verify that all circuits are de-energized using a suitably rated meter.
• Never energize this equipment with the covers removed.
• Replace all devices and covers before turning on power to this equipment.
• The DC conductors of this photovoltaic system are ungrounded and may be energized.
AC Cable
Connection
Battery Cable
Connection
AC Breaker
Lock Out & Tag Out
Lock Out & Tag Out
Remove the PDP cover.
1
BatteryAC
2
Remove the AC knockout plugs and set
aside.
3
Install the cable gland strain relief (not
supplied) onto the knockout hole.
4
Remove the DC knockout plugs and set
aside.
5
Install the cable gland strain relief (not
supplied) onto the knockout hole.
NOTE: For more information, see the Conext Mini Power Distribution Panel Installation
Guide (975-0735-01-01).
Total weight
IP rating
Mounting Location
208.4 lbs (94.5 kg)
NEMA Type 1
Indoor only
DIMENSIONS
For more information, see the Install
or Owner’s manual for each device.
46.41in
1178.7mm
35.34in
897.7mm
16in
406.4mm
16in
406.4mm
44.69in
1135mm
0.59in
15mm
0.39in/10 mm
clearance x6
0.65in
/16.5mm
keyhole x6
12in
305mm
DC+
Ground
DC–
Neutral
LI N L2
LOAD
LI N L2
GRID
(AC1)
LI N L2
GEN
(AC2)
AC OUT AC IN AC IN
LOAD BYPASS GRID
Add UL/CSA approved strain relief
clamps to knockout holes.
AC SOURCE
Install DC cables (not provided)
between the battery disconnect
terminals and the Mini PDP’s
battery terminal lugs. NOTE: For
the Conext Battery Monitor to
work, the provided shunt must be
wired to the battery (see the
Conext Battery Monitor Owner’s
Guide
for details).
Use either bolted or screw
terminals. Torque according
to posted guidelines.
Install AC wires (not provided)
between the L1 and L2 bypass
terminal lugs AND the AC source
box. Install Neutral and Ground
wires (not provided) between the
Neutral and Ground bus bars
AND the AC source box.
Route the wires through one of
the knockout holes.
NL2 L1
Install the Battery Temperature Sensors (BTS) for the inverter
and battery monitor. If stacking with other cables, stack the
sensor on top of the power cable. Install sensors at the
hottest area of the battery bank.
For details, see the Install manuals for each device.
The loose ends will be attached to the PDP for transport.
See markings for details.
BTS
Connect the supplied RJ45 connector to the Pre-Scaler.
NOTE: Due to cable length, the Pre-Scaler must be located
within 3m of the bottom edge of the Quick Fit panel. For details
about Pre-Scaler and shunt connections, see the
Conext
Battery Monitor Owner’s Guide (975-0691-01-01).
Conext™ Quick Fit XW Pro
865-6848-21QF
Complete the commissioning and configuration procedures in the following documents
to commission each device on the Conext Quick Fit XW Pro:
• Conext Gateway Owner’s Guide (975-0806-01-01)
• Conext XW Inverter/Charger (Conext XW Pro NA) Installation Guide (975-0800-01-01)
• Conext Battery Monitor Owner’s Guide (975-0691-01-01)
• Conext System Control Panel Owner’s Guide (975-0298-01-01)