Conext XW PRO 6848 6,800W 48V Manual
Table Of Contents
- Safety Information
- Label Symbols
- Radio Frequency Interference Notices
- Audience
- About
- Product Safety Information
- Introduction
- Pre-Installation Planning
- Wiring
- Removing the AC Access Panel and PDP Internal Faceplates
- Communication Ports and BTS Port
- Wiring the Conext XW Pro with a PDP
- Basic Functional Test – Single Inverter
- Wiring Additional Conext XW Pro units with a PDP
- Basic Functional Test - Multiple Inverters
- Wiring the Conext XW Pro Inverter/Charger without a PDP
- Communication
- Access Installation
- Specifications
- Wiring Diagrams
- Converting Split-phase to Single-phase
Wiring for connections between the PDP and the inverter load sub-panel is not included.
Power distribution jumpers in the PDP accept up to a #2/0 AWG (9.27 mm
2
) cable
(maximum).
See "Torque Values" on page40 for torque requirements.
To install the inverter load sub-panel and AC conduit:
1. Choose a location for the inverter load sub-panel and install it according to the
manufacturer’s directions.
2. Install an AC conduit between the PDP and the inverter load sub-panel.
3. Determine which circuits the Conext XW Pro will power and install the appropriate
circuit breakers into the inverter load sub-panel.
4. For on-grid systems:
a. Disconnect all power to the main AC panel (utility grid).
b. Choose which circuits will be backed by the inverter(s), and remove their
wires from the main panel.
c. Reroute these wires to the new inverter load sub-panel.
5. Remove unused breakers from utility panel.
6. Install a 60amp maximum (disconnect) main circuit breaker in the inverter load sub-
panel.
NOTICE
BACK FED AC POWER
Back fed AC Power can damage equipment. Do not wire the inverter’s AC output port
directly to the utility line or generator output.
Failure to follow these instructions can result in equipment damage.
To connect the Power Distribution Panel (PDP) to the Inverter Load Sub-Panel
and Utility Grid:
1. Connect L1 (from the L1 output jumper) and L2 (from the L2 output jumper), Neutral,
and Ground to your inverter load sub-panel.
2. Connect the ground wire between the PDP and the main AC Panel (utility grid).
3. Connect Neutral from the PDP to the main AC panel (utility grid).
4. Connect L1 and L2 from the input side of the 60 A, 120/240 VAC, two-pole, Type
QOU AC1 breaker (L1 and L2 jumpers) to the main AC panel (utility grid).
Wiring Conext XW Pro Installation Guide
990-91228A-01 This manual is intended for use by qualified personnel 66