Conext XW PRO 6848 6,800W 48V Manual
Table Of Contents
- Safety Information
- Label Symbols
- Radio Frequency Interference Notices
- Audience
- About
- Product Safety Information
- Introduction
- Pre-Installation Planning
- Wiring
- Removing the AC Access Panel and PDP Internal Faceplates
- Communication Ports and BTS Port
- Wiring the Conext XW Pro with a PDP
- Basic Functional Test – Single Inverter
- Wiring Additional Conext XW Pro units with a PDP
- Basic Functional Test - Multiple Inverters
- Wiring the Conext XW Pro Inverter/Charger without a PDP
- Communication
- Access Installation
- Specifications
- Wiring Diagrams
- Converting Split-phase to Single-phase
Figure 47 DC Connections for a Triple-Inverter System
Preparing the Power Distribution Jumper (for Triple-Inverter System Only)
Each Connection Kit for INV2 INV3 PDP includes four, four-tab power distribution
jumpers. In a triple-inverter system, only three tabs per jumper are needed.
Depending on your installation, you will need either:
n Four jumpers for an installation with a single AC source (AC1 or AC2), or
Six jumpers for an installation with two AC sources(AC1 and AC2)
n Cut away one of the four tabs on each jumpers that you will need for your installation.
Installing Breakers
Wiring a second and third Conext XW Pro requires the installation of 60 A, 120/240 VAC,
two-pole, type QOU AC breakers (included with the Conext 120/240VAC Breaker Kits).
To install breakers for a triple-inverter system:
1. In the PDP, disconnect all AC wires (from the utility grid or generator and to the
inverter load sub-panel) and remove the pre-installed two-tab jumpers connected to
the top and bottom terminals on the AC breakers.
Wiring Conext XW Pro Installation Guide
990-91228A-01 This manual is intended for use by qualified personnel 84