6. Install the V-Band clamp and the BOV and orient it as shown. Tighten the clamp using a 4mm hex
socket or Allen wrench. SEE FIGURE 13.8 & 13.9
FIGURE 13.8
Figure 13.9
7. The intercooler piping will be installed starting with the compressor side of the turbo, through the
passenger side of the vehicle, into the front mount intercooler, then up through the driver side of
the vehicle into the throttle body. SEE FIGURE 13.1
8. There are two (2) 90 degree couplers included with the kit. Using the longer 90* elbow, install it
onto the compressor outlet of the turbo facing towards the passenger fender. Use a provided T-Bolt
clamp to hold it loosely in place. SEE FIGURES 13.10 & 13.11