INITIAL SYSTEM ST ART-UP
Now that you have completed installation, you are almost ready to start the watermaker for the rst
time.
Starting with the Seawater valve in the “Seawater Intake” position and the Fresh Water valve in the
“To Flush Tank” position, place the hose labeled “To ush tank” into a clean 5 gallon bucket.
Start the generator and bring it to operating temperature and RPM.
Turn on the Seawater Lift Pump using the switch on the Control Panel labeled “Seawater Lift Pump.”
Verify water is owing out the Brine Dump through-hull.
►►►Take a moment to check for leaks.
Turn on the High Pressure Pump using the switch on the Control Panel labeled “H.P. Clutch.”
Take a moment to check for leaks again and verify additional ow through the system.
Let the system run for 5 minutes and then increase the pressure by turning the Pressure Adjustment
Needle Valve clockwise until it reaches 700 psi.
Do another quick check for leaks.
Pre Start-up Checklist
All hose ttings are secured with hose clamps.
Through-hulls are open.
All wiring connections are secure.
Breaker is on.
Belt tension on High Pressure Pump is adjusted.
Verify Pressure Adjustment Needle Valve is turned counterclockwise to reduce pressure.
Purge Pre- lter of air by pushing and holding the red button on top of the Pre- lter Housing
and turning on the Seawater Lift Pump. Continue to hold the button until air stops being
released; as soon as water is seen, release the button.