Specifications
Your local Seresco representative:
1-888-Seresco (737-3726)
For more information visit www.seresco.net
Design
Checklist
System design and air flow pattern
Evaporation rate and latent loads
Required Access Space
Exhaust Air
Supply Air
Cooling and Heating loads
Outdoor Air
Project: ____________________________________________________________________
Reviewed by: ________________________________________________________________
System design and air flow pattern
All exterior windows, doors and skylights
are fully blanketed with supply air.
No stagnant areas including the water
surface.
Vapor retarder is installed on the warm
side of the dew point in the roof and
walls.
Evaporation rate and latent loads
Pool load calculated.
Outdoor Air load calculated.
Water features reviewed with factory.
Spectators and swim meet mode
calculated.
Required Access Space
Unit is accessible.
Unit has adequate service clearance.
Suspended unit has unobstructed
access.
Exhaust Air
Exhaust fan identified on the plans.
Exhaust Air is minimum 110% the
outdoor air CFM.
Exhaust air drawn from the whirlpool or
any other warm or highly active water
area.
Supply Air
System delivers 4 air changes per hour
or greater.
Supply air is delivered to the deck area.
No short-circuiting of supply air to the
return duct.
Cooling and Heating loads
Sensible cooling load has been
calculated for the space design
temperature.
Heating load has been calculated for the
space design temperature.
Outdoor air has been included in all load
calculations.
Outdoor Air
1.0 CFM/ft² of water and wet deck for
pool with water features.
0.5 CFM/ft² of water and wet deck for
regular pool.
15 CFM per spectator.
Comments:
_________________________________
_________________________________
_________________________________
_________________________________