6. Set the determined installer password and press the knob.
The Sunny remote control is in the installer mode.
7. Select the 700# Operator Level menu and press the
knob.
8. Select the 700.01 ActLev parameter, press the knob and
set to Expert.
9. Confirm the <accept Y/N> query with Y.
10. Set the following parameters to the specified values only if the Sunny Island units are used in systems for own
consumption optimisation:
Number Name Value
261.03 Season enable No
262.01 ProtResSOC 3%
262.02 BatResSOC 2%
262.03 BUResSOC 1%
262.04 PVResSOC 5%
262.05 MinSlfCsmpSOC 89%
Figure 4-39: SMA on-grid parameters
In order to optimise the efficiency of the battery, the battery automatically executes a learning cycle at
periodic intervals, wherein the actually usable capacity of the battery is automatically determined.
In this learning cycle, the battery must cover the SOC limits of 100% and 12% as frequently as possible.
The learning cycle starts at 100% SOC (battery full) and ends at 12% SOC. If both incidents occur in succession
and, in the meantime, the energy is not charged more than 20% SOC, then the learning cycle is evaluated as
“successfully executed”.
The higher the frequency of execution of this learning cycle, the more precise is the SOC calculation.
The higher the frequency of execution of this learning cycle, the more the energy that the battery can save