Installation Manual RESU 10H SEG Type-R

Commissioning
28
4.2
Put the battery pack in operation by taking the following steps :
Powering up the battery pack
4.3
To shut down the battery pack, follow these steps :
Shutting off the battery pack
1.
Turn o the inverter.
2. Remove the wiring box cover.
3.
5.
CAUTION
Turn o the battery pack by moving the Circuit Breaker switch to the OFF
position.
Turn off the disconnect switch.
Close wiring box cover.
4.
WARNING
Do not turn off the disconnect switch at normal operation (Charge/
Discharge/Idle).
If not commissioning after installation or there is any fault on the battery
pack, turn off the Circuit Breaker, then turn off the disconnect switch.
1. Remove the wiring box cover.
2. Turn on the disconnect switch after installation battery pack. Make sure that
the Circuit Breaker switch is in the OFF position
(including Trip position)
3. Move the Circuit Breaker switch to the ON position.
4. Seconds after the Circuit Breaker switch is ON, 4 LEDs will be lit.
5. Make sure that ON indicator is on and see if the battery pack is successfully
initialized. The power on indicator on the front should turn on in green.
6. Close wiring box cover.
7. Turn on the inverter.
If it stays off, indicates FAULT or fails to operate, do not use the battery
pack and contact LG Chem (page 34) or your distributor.