14 ProtoMat 95s/II
3.6 Initialization
The following initialization procedures have been carried out on the
ProtoMat
95s/II by LPKF at the factory so that the positions of the plotter
head and auxiliary clamp have been defined and preset (see „Functions
in BoardMaster“ on page 29.).
1.
Plotter head over the transfer station (exchange position)
2.
Auxiliary clamp over the transfer station
3.
Auxiliary clamp over the first tool in the tool magazine
4.
Auxiliary clamp over the last tool in the tool magazine
Description of the transport securing devices:
fig. 1: Transport securing devices
on the LPKF ProtoMat 95s/II
Note: Keep all transport securing devices and reattach them
accordingly if the machine is to be shipped again.
The packaging should also be kept and used when the machine is
returned for servicing.
1
- Securing device 1: To secure the machine to the transportation base - M5 x 25, 4.5 x 60 bolts
2
- Securing device 2: To secure the x-axis - M4 x 10 bolts
3
- Securing device 3: To secure the y-axis - M4 x 40 screw
4
- Securing device 4: To secure the plotter head - Clamping wedge
5
- Securing device 5: To secure the tool magazine - Expanding wedge
4
123
5