User Manual
Desigo workflow, tools and programming
Workflow for primary systems
4
44 | 353 CM110664en_07
make changes to the same automation station. This way no inconsistent data
can be created.
To quickly transfer project data, the data is compressed before it is sent from
the computer to the server. The data is managed on the Branch Office Server.
The project creator transfers the data from his local hard disk to the server.
In large projects the data can be moved in two steps:
1. Step: Part of the project is transferred from the Branch Office Server to a
computer in the plant.
2. Step: Parts of the transferred project can be transferred to local computers.
This is called a sequential check-out.
Parts of the project, such as the building or network topology are checked out
in read-only mode, so that all users always have the project overview.
Working in parallel during engineering
Several users can work on different automation stations in the same project at
the same time. To do this, data is transferred from the central data storage on
the Branch Office Server to the local hard disks, e.g., individual automation
stations are being commissioned at the customer's site while some automation
stations are still being engineered at the office.
Working in parallel during commissioning
Several users can work on different automation stations in the same project at
the plant at the same time. To do this, the components to be loaded are
transferred (Pack & Go), so that the user, e.g., can load the configuration or
program and then perform the point test. The test results are saved in the
automation station and can be viewed and transferred back to the engineering
database by the commissioning engineer at any time.
Working in parallel during service
A service technician can connect with the plant by remote and make changes.
To do this, data is transferred from the Branch Office Server to the local hard
disk. After the technician is done, the changes are transferred back to the
Branch Office Server, so that the project database is up-to-date again.
Subcontracting
Project-specific solutions can be developed outside the project organisation
and specific tasks, such as configuration and point test can be outsourced to
subcontractors.
If you outsource specific tasks, make sure that:
● The work packages for the subcontracting can be easily transferred to the
subcontractor
● The subcontractor's work can be documented
● The changed data can be transferred back to the engineering database
4.7 Workflow for primary systems
XWP Project Manager
Create project: