Product Description
The temperature transmitter equipped Duct
Averaging Sensor assemblies sense the average air
temperature in ductwork where mixing baffles are
not provided or where stratification occurs. Each
sensor assembly mounts on sheet metal ducts.
Contents
Short, rigid platinum RTD averaging element
4 to 20 mA transmitter
Two wire nuts
Electrical box for wiring connections
Product Numbers
Product
Number
Sensing
Element
Range
535-490-XX
100 Pt (385α)
20°F to 120°F
(-7°C to 49°C)
XX Probe Length in Inches (cm)
18
18 (46)
24
24 (61)
36
36 (91)
48
48 (122)
Caution Notations
CAUTION:
Equipment damage or loss of
data may occur if you do not
follow a procedure as
specified.
Required Tools
Wire cutters
Small 1/8-inch flat-blade screwdriver
Medium flat-blade screwdriver
Four No. 10 × one-inch sheet metal screws
Electric drill and one-inch drill bit
No. 27 drill bit for screw holes
Expected Installation Time
535-490-18 or 535-490-24 1.5 hours
535-490-36 or 535-490-48 2.0 hours
Prerequisite
Field wiring must be pulled to installation site.
Installation
1. Mark the location of four holes on the duct at the
place where the unit is to be mounted (see
Figure 3). Mark the location in the center of the
four mounting holes for a one-inch clearance
hole.
2. Drill the one-inch clearance hole. Switch drill bit
to the No. 27 bit and drill the four sheet metal
mounting screw holes in the duct.
3. Remove the 2-inch × 4-inch electrical box cover
on which the transmitter is mounted.
4. Pierce the rubber gasket for all four mounting
screw locations with the small screwdriver. Push
the mounting screws through the holes in the
gasket from the inside of the 2-inch × 4-inch
electrical box.
5. Place the unit on the duct into position and
fasten it in place with the four mounting screws.
CAUTION:
The 36-inch and 48-inch probes must be
supported within six inches of the tip of the probe.
6. Connect the conduit to the utility box.
7. Pull Field wiring to utility box.
8. Strip the field wires with wire cutters and
connect the positive (+) 26V lead wire to the
transmitter's PWR wire. Connect the signal lead
wire to the transmitter's SIG wire. See Figure 1
and Table 1.
9. Replace the 2-inch × 4-inch electrical box cover
on the transmitter assembly box.
The installation is now complete.