Installation Instructions

Installation Instructions
Document No. 129-565
April 28, 2015
EcoView™ 8 DO Module Installation and Commissioning
Item Number 129-565, Rev. CA Page 1 of 5
This document covers the installation and
commissioning of the EcoView8 DO Module.
See the following documents for installation of other
EcoView system components:
EcoView Touchscreen Installation and System
Start-up
(129-562)
EcoView Thermostat Installation Instructions
(129-564 or 129-566)
EcoView Multi-phase Meter Installation
Instructions
(129-563)
Product Description
The EcoView 8 DO Module is an eight-channel, pilot-
duty controller module that is used to manage lighting
or other energy-consuming electrical loads that would
benefit from scheduling. Relay channels may be
accessed through the EcoView Touchscreen or
remotely through the EcoView Web application.
Product Number
57-002
EcoView I/O Module, 8 DO, with Zigbee,
includes power supply
Caution Notations
CAUTION:
Equipment damage or loss of
data may occur if you do not
follow the procedures as
specified.
Required Tools and Materials
Flat-blade screwdriver (1/8-inch blade width)
Wire strippers
Expected Installation Time
15 minutes for installing the EcoView 8 DO Module
30 minutes for wiring each DO
Prerequisites
NOTE: If the EcoView 8 DO Module will be directly
controlling line voltage, it must be mounted in
an appropriate plastic NEMA enclosure.
The EcoView Touchscreen is installed and started up
according to the
Installation Instructions
(129-562).
A 120 Vac outlet is available for the EcoView 8
DO Module power supply.
Depending on the type of installation, other
prerequisites may have to be completed.
Installation
Always wear an electro-static discharge
(ESD) wrist strap and discharge
accumulated static before touching field
panel components.
Install the EcoView 8 DO Module near the loads
to be controlled.
1. If the EcoView 8 DO Module will be directly
controlling line voltage, mount the plastic NEMA
enclosure in the desired location.
2. If necessary, install a standard 120 Vac outlet in
the enclosure where the EcoView 8 DO Module
power supply will be attached.
3. Using the provided screws, mount the EcoView 8
DO Module assembly in the enclosure.
4. Attach the EcoView 8 DO Module 24 Vac power
supply to the standard 120 Vac outlet and secure
with the provided plate screw.
5. Wire the individual circuits to be controlled to the
2-pin connectors for Relay 1 Relay 8.
NOTE: The relays are capable of controlling loads up
to 240 Vac at 3A. Anything outside of this
range should be controlled by contactors.