5
5.1
Commissioning guidelines
Procedure
Proceed as follows to commission the inverter:
1.
Define the requirements
of your application
placed on the drive.
(Page 86) .
2.
Reset the inverter when
required to the factory
setting.
(Page 90) .
3.
Check whether the
factory setting of the
inverter is appropriate for
your application.
If not, start with the basic
commissioning.
(Page 91).
4.
Check whether you need
to adapt the functions of
the terminal strip that you
specify in the basic
commissioning.
(Page 103).
5.
If necessary, adapt the
co
mmunications interface
in the inverter.
(Page 117) .
6.
If necessary, set further
functions in the inverter.
(Page 141) .
7.
Save your settings.
(Page 251) .