9.5 MOVA Commissioning Checklist
The following checklist should be used to commission a Siemens MOVA unit. The steps
are expanded upon in section 9.6, which starts on page 150.
If an OMCU and MOVA unit is being installed, it is recommended that the OMCU
application be commissioned before the MOVA application. The checklist should be
followed in sequence:
Step
Section
Action to be Performed
1)
5
Check that the MOVA unit has been installed correctly.
2)
6
Check that the OMCU has been commissioned correctly (when an
OMCU and MOVA unit is being installed).
3)
5.2.8
Ensure the RAM backup battery insulation strip has been removed.
4)
9.6.7
All the cables can be connected since the unit can now be re-
initialised after the correct site data has been loaded to ensure a
‘clean start’.
5)
-
Switch on the MOVA unit’s mains supply.
6)
7.3.1
Check that the System LED (LP1) is flashing. Note that MOVA will
flash this LED at the fast rate since the unit is not ‘On Control’.
7)
9.6.1
Connect the PC to the MOVA unit’s local port (the 25 way D-type
connector on the front of the processor board) and start the MOVA
communications application.
8)
9.6.2
Initialise MOVA by entering the handset command INI=2. If the
OMCU application is not required, enter INI=3 to completely re-
initialise the whole unit. Enter LDV=7 to request the MOVA facility.
Refer to section 9.8 if running dual stream MOVA
Refer to Appendix D for MOVA 4
9)
Step deleted