9.6 MOVA Commissioning Detail
This section expands on the steps in the commissioning checklist from the previous
section…
If an OMCU and MOVA unit is being installed, it is recommended that the OMCU
application be commissioned before the MOVA application. The checklist should be
followed in sequence:
Step
Section
Action to be Performed
1)
5
Check that the MOVA unit has been installed correctly.
2)
6
Check that the OMCU has been commissioned correctly (when an
OMCU and MOVA unit is being installed).
3)
5.2.8
Ensure the RAM backup battery insulation strip has been removed.
4)
9.6.7
All the cables can be connected since the unit can now be re-
initialised after the correct site data has been loaded to ensure a
‘clean start’.
5)
-
Switch on the MOVA unit’s mains supply.
6)
7.3.1
Check that the System LED (LP1) is flashing. Note that MOVA will
flash this LED at the fast rate since the unit is not ‘On Control’.