Installation Instructions

Installation Instructions
Document No. 546-14407
August 14, 2013
LCM-OAVS VAV Room Pressurization with BTU
Compensation, HW Reheat and Fast Damper
Actuation (One Exhaust, One Supply)
Item No. 546-14407, Rev. EA Page 1 of 6
WARNING:
LCM-OAVS will be damaged/destroyed if
offboard Air Module(s) are not wired
correctly. For more information, see the
Wiring Diagrams section.
Product Description
This Lab Controller Module (LCM) features VAV
control of a laboratory room with one supply duct,
one exhaust duct, and up to six Fume Hoods. It uses
fast-acting electronic actuators to control the supply
and general exhaust dampers, and can operate
stand-alone, with a field panel, or networked.
This LCM is built on an OAVS board (Offboard AVS)
and has no air velocity transducers on the board.
Instead it has inputs for up to two AVS signals.
Offboard Air Module(s) house AVS transducer(s)
and send signal(s) to the AVS input(s) on the LCM
OAVS board.
Shipping carton contains a controller assembly
(controller board and cover), a mounting rail, and
two self-tapping screws.
NOTE: Keep the controller in its static-proof bag
until installation.
Product Numbers
Product Description
550-767E
LCM-OAVS — with HW Reheat and Fast
Damper Actuation One Exhaust, One
Supply
Control Applications 2621 (and 2627 with
BTU Compensation)
Requires Offboard Air Module(s) order and
ship separately
550-818B
Offboard Air Module (OAM) – order
separately
GNP191.1U Siemens Industry fast-acting electronic
actuator order and ship separately
Warning/Caution Notations
WARNING
Personal injury or loss of life
may occur if you do not follow
the procedures as specified.
CAUTION
Equipment damage or loss of
data may occur if you do not
follow procedure as specified.
Required Tools
Electro-Static Discharge (ESD) wrist strap
Small and medium flat-blade screwdrivers
Electric drill
1/4-inch (6.35 mm) hex nut bit
Additional tools if not using self-tapping option:
1/4-inch nut driver
1/8-inch (3 mm) bit
Prerequisites
Wiring conforms to NEC and local codes
and regulations.
Field level network (FLN) with 24-volt wiring.
Supply power to the unit is OFF.
Any necessary hardware installed: terminal
unit, actuator(s), sensor(s), etc.
Room Temperature Sensor (RTS) installed
(optional). Note: A low-cost temporary RTS
(P/N 540-658P25) is available that plugs into
the RTS port on the LCM-OAVS, providing
temperature input and actual space control
until a permanent RTS is installed.
Expected Installation Time
New controller installation
10 min.
Replacement - removable terminal blocks
6 min.
Replacement without removable terminal
blocks
16 min.
NOTE: You may require additional time for
database work at the field panel.

Summary of content (6 pages)