Commissioning Instructions

Table Of Contents
Before You Begin
Verifying Power
6
Siemens Industry, Inc. Start-up Procedures 140-1321
Restricted 2015-11-04
CAUTION
The FHC-OAVS has two terminal blocks with terminations numbered identically
(terminations 1 through 16). DO NOT mix these up with each other.
If the FHC-OAVS is not connected as shown, it is not resistant to electrical surges. It
is also susceptible to interference from other equipment.
CAUTION
A separate power supply is required if a 4-20 mA sensor is used.
Failure to follow wiring precautions will result in equipment damage.
Verifying Power
1.
Verify that the controller has 24 Vac power and that the fuse has been inserted
into the trunk or that power to the transformer is ON.
2.
Verify that the Basic Sanity Test (BST) LED on the controller flashes once per
second.