Main menu > Commissioning > Extra configuration > Aggregates > Heat demand >
Operating line Range Setting
Primary controller Yes, No Yes
Main menu > Commissioning > Settings > …. or
Main menu > Settings > Controller 1 > Setpoints >
Operating line Range Setting
Setpoint high 500.0 °C > x > Setpoint low 70.0 °C
Setpoint low Setpoint high > x > -50.0 °C 70.0 °C
Main menu > Commissioning > Communication > Distribution zones >
Operating line Range Setting
Heat distribution zone 1…31 1
Heat distr zone source side ----, 1…31 2
Main menu > Commissioning > Settings > Aggregates > Heat demand >
Operating line Range Setting
Heating flow setpoint 0…140 °C 70 °C
Flow temperature reduction
max
0…100 K 30 K
Main menu > Commissioning > Settings > Controller 1 > Setpoint effects >
Operating line Range Setting
[Setp compensation 1] delta -50.0…+50.0 K 30 K
[Setp compensation 1] start -50.0…+500.0 °C 70 °C
[Setp compensation 1] end -50.0…+500.0 °C 40 °C
Configuration
Controller settings
Communication settings
Heat demand
Universal shift