15.1.3 Pump outputs
Only one pump can be assigned to each sequence. However, each pump can be
controlled by max two sequences.
Pump for heating coil on sequence 2.
A
y1 y2 y3
A
M
DO
y2
730
720
Mod output
MECH
HR
15.1.4 Control parameters (P-bands, integral action times)
For every configured sequence, a P-band (Xp), an integral action time (Tn) and a
derivative action time (Tv) can be set.
Integration action time Tn = 00:00: The controller operates in P- or PD mode.
Derivative action time Tv = 00:00: The controller operates in P- or PI mode.
For fast commissioning of the controller, we recommend the following:
Set integral-action time Tn equal to the greatest time constant of the controlled
path
Set the derivative action time Tv of the controller equal to the time constant of
the measuring sensor
Main menu > Commissioning > Settings > .... or
Main menu > Settings > Controller 1..3 > Control parameters >
Operating line Range Factory setting
[Sequence 1 \_ ] Xp 30 K
[Sequence 1 \_ ] Tn 00.00...59.55 m:s 03.00 m:s
[Sequence 1 \_ ] Tv 00.00...59.55 m:s 00.00 m:s
[Sequence 2 \ .._ ] Xp 30 K
[Sequence 2 \ .._ ] Tn 00.00...59.55 m:s 03.00 m:s
[Sequence 2 \ .._ ] Tv 00.00...59.55 m:s 00.00 m:s
[Sequence 3 \ .. .._ ] Xp ¹
)
30 K
[Sequence 3 \ .. .._ ] Tn ¹
)
00.00...59.55 m:s 03.00 m:s
[Sequence 3 \ .. .._ ] Tv ¹
)
00.00...59.55 m:s 00.00 m:s
[Sequence 4 _/ ] Xp 30 K
[Sequence 4 _/ ] Tn 00.00...59.55 m:s 03.00 m:s
[Sequence 4 _/ ] Tv 00.00...59.55 m:s 00.00 m:s
[Sequence 5 _.. / ] Xp ¹
)
30 K
[Sequence 5 _.. / ] Tn ¹
)
00.00...59.55 m:s 03.00 m:s
[Sequence 5 _.. / ] Tv ¹
)
00.00...59.55 m:s 00.00 m:s
¹
)
only available in controller 1
Application example
Setting values