27 Heating/cooling changeover
The heating/cooling changeover function block is used to change over the
operating mode (heating or cooling) in 2-pipe systems.
The preselection heating/cooling is generated on the device or received as a
heating/cooling signal from the bus.
x
Q
23
H/C changeover
The following types of changeover are available for operating mode preselection
H/C:
Changeover with operating mode selector via operation
Changeover with analog input (e.g. to change over by outside temperature or by
flow temperature)
Changeover with digital input (e.g. to change over via manual switch or via
changeover thermostat in the flow)
Changeover by date
If several changeover types are active, the operating mode is determined by the
following priority selection:
1. Operating mode selector
2. H/C changeover input
3. Heating/cooling acc to calendar
The preselected operating mode heating/cooling is provided in the heat and
refrigeration distribution zone to all other controllers within the same zone.
In a hydraulic circuit, the operating mode heating/cooling can be preselected only
via one point. If several changeover signals are sent simultaneously to the bus
within the same distribution zone, a fault message is generated.
The preselected operating mode input H/C should be activated at the precontroller
or generator where possible.
27.1 Activate function
To activate the function, Yes must be set in operating line "2-pipe heating/cooling
system".
Main menu > Commissioning > Extra configuration > Heating/cooling ch'over >
Operating line Range Factory setting
2-pipe heating/cooling system No, Yes No
Application
Recommendation
Configuration