Basic Documentation

52/332
Siemens Universal controllers RMU710B, RMU720B, RMU730B CE1P3150en
Building Technologies Operating modes 03.10.2011
It is possible to enter if during the holiday period operating mode Economy or
Protection is to be used.
Main menu > Room operating mode > (basic types A, U)
Main menu > Time switch 1 > (basic types P and C)
Operating line Range Factory setting
Room operating mode
holidays
Economy, Protection Economy
If the controller is connected to other controllers via communication, the
corresponding operating mode applies.
6.10.3 Special days
Special days are periods of time when the building is used for special purposes
and whose start and duration are known in advance.
Visitor days in special homes
Religious holidays in churches
The 7-day program allows for an additional 24-hour program (special day) as a
special day program.
See section 6.9.2 "Time switch entries" for settings.
If the controll
er (master) is connected to other controllers (slaves) via
communication, a specific 7-day program can be entered as a special day on each
controller (slave). The time of the special day is communicated by the master and
applies to all controllers in the same holidays / special day zone.
6.10.4 Calendar entry
Max 16 entries can be made. The entries are sorted in chronological order. The
following is required for each entry:
Date, year and start time
Date, year and end time
Reason for entry (holidays or special day)
Main menu > Holidays / special days >
Operating line Range Factory setting
Entry 1...16 Start
End
Reason
Annually recurring holidays or special days can be entered by entering an asterisk
"*" for the annual setting. Otherwise, the entries made are automatically deleted at
the end of the holidays or special days.
If two entries overlap, the following applies: Special days have priority over
holidays. It is thus possible to predefine a special day during the holiday period.
Example of a special day during the holiday period: Stage play in the school
building.
At the end of the holidays or special day, operation according to the normal 7-day
program is resumed. During this transition, it is possible that the optimum start
control (e.g. boost heating) cannot be started in time. We thus recommend to move
down the end of the holidays giving the plant sufficient time to adapt to the
respective setpoints.
Setting values
Examples
Setting values
Priority
Example
Note