Operating Instructions
Installation Instructions
Siemens Building Technologies, Inc. 7
Installation Instructions
Environmental Conditions
Install the Conventional Bypass Option in a heated, indoor controlled environment that is free of
moisture and conductive contaminants such as condensation and dust. The air entering the unit
for ventilation/cooling must be clean and free from corrosive gases.
The ambient temperature must be between 14°F and 104°F (-10°C to 40°C) and the relative
humidity must be 0% to 95% non-condensing.
Mechanical Installation
Inspection
1. As you unpack the Conventional Bypass Option, check for shipping damage. In
the event of damage, contact the transport company.
2. Locate the Conventional Bypass Option nameplate and confirm that the unit is
configured to the installation requirements.
3. Verify that the delivery is complete. If not, contact the supplier.
Dimensions and Weights
Figure 3 shows overall and mounting dimensions for the Conventional Bypass Option. Figures 4
through 7 show conduit locations.
Approximate weights are as follows.
Bypass
Frame Size
∆ Weight lb
(kg)
A 55 (25)
B 65 (29)
C 100 (45)
D 170 (77)
E 200 (91)
F 500 (227)
NOTE: Exact weight will be
affected by actual
horsepower/voltage
and selected power
options.