Operating Instructions
Start Up Procedures
Siemens Building Technologies, Inc. 25
Quick Commissioning Procedure, Continued
Parameter Description Action Setting/Default
P0010
Quick Commissioning
0 = Ready to Run
1 = Quick Commissioning
30 = Factory Setting
1. Press
to access parameter r0000
and to enter the SED2 parameter mode.
2. Repeatedly press
to advance to
parameter P0010.
3. Press
to access the parameter
values level.
4. Press
to advance to 1.
5. Press
to confirm and save the
P0010 = 1 setting.
Setting = 1
Default = 0
NOTES:
1. P0010 must always be set back to 0 before operating the motor.
2. If P3900 is greater than 0 on completion of commissioning, P0010 is automatically set back to 0.
P0100
Operation for Europe/N.
America
0 = 50 Hz, kW (Europe)
factory default
1 = 60 Hz, hp
(North America)
The setting of Motor
Frequency and Unit of
Measurement DIP switch 2
overrides P0100 settings 0
and 1.
1. Press
to advance to parameter
P0100
2. Press
to access the parameter
values level.
3. Press
to advance to 1.
4. Press
to confirm and save the
P0100 = 1 setting.
Setting = 1
Default = 0 or 1
Default is
determined by
the setting of
the motor
frequency and
unit of
measurement
DIP switches.
NOTES:
1. Stop the SED2 (that is, disable all pulses) before changing this parameter.
2. Changing P0100 resets all rated motor parameters as well as other parameters that depend on the rated
motor parameters (such as P0340, Calculation of motor Parameters).
P0304*
Rated Motor Voltage
10V to 2000V.
Rated motor voltage (V)
from motor nameplate.
1. Press
to advance to parameter
P0304.
2. Press
to access the parameter
values level.
3. Press
to advance to nominal
voltage.
4. Press
to confirm and save the
setting.
Setting =
Motor
nameplate
Default =
Varies by
model
* Motor related parameters.