First you need to insert a grower washer or a lock washer and a grounding lug into a hexagon socket screw
M4x10. And then you must screw it into the hole provided for this purpose on the side of the station. The
correct tightening torque is of 2.2 N.m. If needed, you can bend the lug to ease the insertion of the wire.
13 CONNECTIVITY
Via ADSL (primary)
Please refer to your provider manual
The base station only accepts the dynamic host configuration protocol (DHCP) on the ETH interface
Via Satellite connexion (primary)
Please refer to your provider manual
The base station only accepts the dynamic host configuration protocol (DHCP) on the ETH interface
Via the 3G network (secondary)
The 3G key is connected directly to the front panel of the base station
The indicator (DEL) on the 3G key will blink for a few minutes and then should stop. At this point color must
be blue or green. The blinking green or blue means: research network.
Blue → fixed connection to 3G networks (depends on the material)
Green → fixed connection to 2G networks (depends on the material)
14 BASE STATION « SWITCHING ON » PROCEDURE
How to switch the base station on:
Switching occurs when the POE+ cable is powered and connected to the base station. Do it at the end of the
installation.