Specifications

Control Interface Module, Continued
Step Procedure
Note: The CAC3 is mounted on the CIM-Base board, which is
located on the inside of the Maxum door. The CAC3 is
highlighted in the blue box in the image below.
4. Disconnect the Ethernet cable from the CAC3 board. It is not
necessary to disconnect the other end of this cable.
5. Remove the CAC3 board by grasping both sides firmly and
pulling up. Do not touch board mounted components.
6. Place the CAC3 in an anti-static bag for return to Siemens.
7. Install the new CAC3 board by pressing it firmly into the
connectors, taking care not to touch any components or
connections on the board. Then, reconnect the Ethernet
cable to the CAC3.
8. Apply power to the Maxum and allow it to boot.
9. Using either Gas Chromatograph Portal (GCP) or System
Manager software, restore the analyzer database using the
.amd file that was saved before beginning the procedure.
10. When the CAC3 is removed, current date and time
information is lost. If the analyzer is configured to obtain date
and time information from a central server, then it will update
automatically. If no time server is set, it will be necessary to
manually set the date and time on the analyzer.
A5E31405710001 4-7